Posted on: June 6, 2018

[ARCHIVED] Westnedge Road Work

469577715

Work to improve South Westnedge Avenue from Romence road to Mall Drive began on June 4 with milling of the roadway surface.  Future improvements include new concrete curb and gutter, sidewalks, ADA ramps, water main hydrant extensions, storm sewer improvements and traffic signal replacement at J L Hudson Drive. Storm sewer improvements includes replacement of existing storm lines and the installation of a storm sewer relief outlet for South Westnedge Avenue east of J L Hudson Drive.

Estimated  Cost: $3,000,000 (MDOT Funding - $700,000)
Anticipated Completion Date: September 4, 2018
Lane closures and traffic shifts began June 4, 2018 with construction work starting June 5, 2018.


PASub

To receive construction updates about this project, register for PortageAlert and select "2018 South Westnedge Avenue Reconstruction" subscription.

Visit the Construction Projects page to view all current construction projects.  Questions about City of Portage construction projects can be directed to the Department of Transportation of Utilities by a contact form or at 269-329-4422.

Additional Info...
Facebook Twitter Email

Other News in Spotlights

gallery at the parks

Gallery at the Parks

Posted on: February 13, 2026
Website Bug

Council Capsule

Posted on: February 11, 2026
Raising Canes SM

Raising Cane's Grand Opening Traffic Plan

Posted on: February 10, 2026
BHM Karaoke and Lip Synch Battle Royale 1200

Karaoke & Lip Synch Battle Royale

Posted on: February 4, 2026
RFB Ramona Fishing Pier

RFB - Ramona Park Fishing Pier Project

Posted on: January 27, 2026

Fall Leaf Collection Update

Posted on: December 22, 2025